Home/Case Studies
— Case Studies

Selected work,
de-identified on request.

Most of our clients prefer not to publish project details. The case studies below describe scope, approach, and outcome, operator names withheld where required.

Plant operators rarely want their corrosion problems on a vendor website, and we respect that. Each case below is real, the engineering decisions described are real, and the outcome is documented in our records. Names are withheld where the contracting party preferred it; representative photography is used where the original installation cannot be photographed.

If you'd like a reference for a project similar to yours, we can usually arrange a direct conversation between operating teams.

01 — Featured Project

Selenium water treatment
tank system.

One of the largest global water treatment companies needed 30 large FRP tanks, plus an integrated raised platform system, engineered, fabricated, and delivered to California in under six months. NSF 61 compliance required throughout.
Water & Wastewater · Municipal Treatment

30 NSF 61 tanks,
delivered ahead of schedule.

Industry
Water Treatment · Municipal
Service
Selenium removal · drinking water
Build
Filament-wound FRP
Tanks
30 × 13 ft dia. × 29 ft
Standards
NSF 61 (drinking water contact)
Delivery
Ontario to California · ahead of schedule

Challenge. Drought conditions in California forced groundwater to travel further to reach treatment facilities, absorbing elevated concentrations of selenium along the way. Selenium is essential in trace amounts but hazardous at high levels. The client needed 30 large FRP tanks, each 13 ft × 29 ft, plus an engineered raised FRP platform spanning the entire tank array, all within a six-month window. Every tank had to meet NSF 61 requirements for drinking water contact.

Approach. Precisioneering dedicated a full crew and a filament winder exclusively to this project. The tanks and the integrated raised FRP platform system were engineered concurrently to keep the schedule tight. All 30 vessels were hydrostatically tested and inspected before leaving the Ontario facility.

Outcome. The complete system, 30 tanks plus the platform, was shipped from Ontario to California ahead of schedule. Precisioneering's delivered price, including cross-continent transportation, was cost-competitive against every other North American FRP tank fabricator that quoted the work.

02 — Recent Projects

Selected work
across industries.

Scope, approach, and outcome at a glance. Full project documentation available under NDA.
Mining & Smelting · Critical Infrastructure
02
Mining & Smelting · Nickel Processing

2,000 ft SOx/NOx hazardous scrubber ducting.

One of the largest global nickel producers needed a full replacement of the SOx/NOx scrubber ducting system at their smelting operation, in three months. The effluent is among the most toxic industrial gases encountered in FRP service; the surrounding city maintains active evacuation plans in the event the scrubber system is compromised. During inspection, a section of duct that had been power-washed and left open for over two weeks still required one inspector to seek medical treatment after exposure.

Standard polymer expansion joints could not withstand the corrosive duty. Precisioneering engineered a custom fiberglass bellows expansion joint purpose-built for the service conditions. Fabrication ran three dedicated stations, 24 hours a day, seven days a week for the full three-month window, and the project was completed on time.

Precisioneering was selected because the client needed absolute confidence that both the engineering and the fabrication schedule would hold. This was designated a critical-risk project; failure to deliver on time or to spec was not an option.

Length
2,000 ft
Diameter
5.5 ft
Service
SOx/NOx · extreme toxicity
Timeline
3 months · on time
Schedule
24 hr/day · 7 days/week · 3 stations
Custom
FRP bellows expansion joint
— Operator Feedback

Our previous vendor sold us tanks. Precisioneering sold us a chemistry decision and the tanks came with it. Three years in, we haven't had a service call.

Plant Manager North American specialty chemical producer · Chemical processing
— What to Send

Quotes start with
three numbers.

If you can send chemistry, temperature, and dimension or capacity, we can come back with a scoped recommendation in two business days. Drawings, P&IDs, and existing equipment specs accelerate the conversation but aren't required to start.

— Reference Conversation

Want to talk
to an operator?

Where the contracting party permits it, we can arrange a direct conversation between your engineering team and a current operator running similar equipment.

Request a Reference Explore by Industry